THE REVISED plan for the school district's construction project, after new cost estimates showed that the original design would not be affordable.
Re-4A building schedule

Asbestos removal will begin in June.
Demolition of the science/vo-ag building will begin early June.
Excavations and foundation work will begin around in early July.
Major structural installation (steel beams, trusses) by August.
August-October: The completion of the locker rooms and the two middle school classrooms connecting middle school to band room.
October-December: Completion of elementary classrooms and the breezeway connection to the cafeteria.
January-March 2014: The completion of the career and technical education center and new high school classrooms.
March-May, 2014: Completion of the exterior including landscape and sidewalks.
May-August 2014: Final construction phase.
September 2014: Ribbon-cutting ceremony to start the school year.

Re-4A revamps construction plans

THE REVISED plan for the school district's construction project, after new cost estimates showed that the original design would not be affordable.
click here to add your event
Cortez ~ Events
click here to add your event
Cortez ~ Events